Project:Construction of proposed Event Hall and guest house Client: private client Contractor:Olu-Ben unique service LTD [b][/b] |
Re: Construction Process Of An Event Hall and guest house by consultmal97(m): 8:23am On Aug 26, 2021 |
Attached is the architectural drawing of proposed Event Hall
|
Re: Construction Process Of An Event Hall and guest house by consultmal97(m): 8:26am On Aug 26, 2021 |
Project duration:6month Note:project duration can be less than 6month but client suggested we go for 6month due to finance plan |
Re: Construction Process Of An Event Hall and guest house by consultmal97(m): 8:39am On Aug 26, 2021 |
Location: Otta Week 1 Mobilization:All material and tools needed for construction is been moved to site Drawing review:As seen in the drawing,the architectural drawing proposed we have column in the middle of the Event hall but for me that too conventional and it also take space out of the needed space of the hall,also columns can be an obstruction for guest sitting at the back of the hall.so therefore reason for removing the Centre columns Modication; We therefore design our columns to span end to end which is about 10.45 width and hall length is about 21m, so we will be having our columns at 3m c/c around the hall perimeter Mobilization |
Re: Construction Process Of An Event Hall and guest house by consultmal97(m): 8:41am On Aug 26, 2021 |
Attached is the proposed Event hall development
|
Re: Construction Process Of An Event Hall and guest house by consultmal97(m): 8:35pm On Aug 30, 2021 |
Week 2 activities 1)Foundation digging of foundation 2)Casting of foundation base(blinding) 3)Placing and aligning of foundation pad reinforcement(commonly called basket) and column starter bar 4)casting of foundation pad 5) foundation block setting |
Re: Construction Process Of An Event Hall and guest house by twinskenny(m): 8:38pm On Aug 30, 2021 |
We do electrical and also low voltage You can check our thread for our previous work pictures I wish you good luck sir https://www.nairaland.com/5681155/electrical-audio-system-cctv-fire |
(1) (Reply)
Introducing MERCYVILLE ESTATE, Ikate, Lekki, Lagos. / 5-bedroom Bungalow For Sale / BEAUTIFUL APARTMENTS FOR SALE,off Freedom Way,Lekki Phase 1/call :+2348167350289
(Go Up)
Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health religion celebs tv-movies music-radio literature webmasters programming techmarket Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 11 |