Is It Realistic To Finish Building 2 Units Of 5 Bedroom Duplexes In 3 Months? - Properties - Nairaland

Nairaland Forum / Nairaland / General / Properties / Is It Realistic To Finish Building 2 Units Of 5 Bedroom Duplexes In 3 Months? (292 Views)

My Landlady And Her Daughter Want To Finish Me! / Cost Of Building 2 Storeys With 6 Units Of 3 Bedroom / 5 Duplexes In Gowon Estate On Fire In Lagos (Photo) (2) (3) (4)

(1) (Reply) (Go Down)

Is It Realistic To Finish Building 2 Units Of 5 Bedroom Duplexes In 3 Months? by nuland(m): 10:01am On Jan 19, 2022
Hello Everyone,
I have very little knowledge about building/construction as I am into ICT.
A friend turned brother who is based in one of the Scandinavian countries has decided to return home finally this year and wants me to help him put up 2 units of 5 bedroom Duplexes.
I am based in Abuja but Our home state where the building is to be erected is less than 2 hours away, meaning I can shuttle between Abuja and home easily.
The snag is, My state is almost a civil service state where most people are government workers who rely on salaries and economic activities are at the lowest ebb you can think of. Finding building construction/construction companies that will take up the job from start to finish hasn't been fruitful.
To the professionals in the house is it feasible to get the building done in 3 Months? ( All needed for the project won't be an issue). I have asked him to give me till the end of February to do a thorough job(Findings) and get back to him.
Your Sincere Contributions shall be appreciated.
Thanks in advance!
Re: Is It Realistic To Finish Building 2 Units Of 5 Bedroom Duplexes In 3 Months? by naijacreativeha(f): 10:12am On Jan 19, 2022
nuland:
Hello Everyone,
I have very little knowledge about building/construction as I am into ICT.
A friend turned brother who is based in one of the Scandinavian countries has decided to return home finally this year and wants me to help him put up 2 units of 5 bedroom Duplexes.
I am based in Abuja but Our home state where the building is to be erected is less than 2 hours away, meaning I can shuttle between Abuja and home easily.
The snag is, My state is almost a civil service state where most people are government workers who rely on salaries and economic activities are at the lowest ebb you can think of. Finding building construction/construction companies that will take up the job from start to finish hasn't been fruitful.
To the professionals in the house is it feasible to get the building done in 3 Months? ( All needed for the project won't be an issue). I have asked him to give me till the end of February to do a thorough job(Findings) and get back to him.
Your Sincere Contributions shall be appreciated.
Thanks in advance!
Yes 3 months is very possible, you can contact me on 09036346989 on WhatsApp or calls for construction. That is what I do for a living
Re: Is It Realistic To Finish Building 2 Units Of 5 Bedroom Duplexes In 3 Months? by nuland(m): 10:20am On Jan 19, 2022
naijacreativeha:

Yes 3 months is very possible, you can contact me on 09036346989 on WhatsApp or calls for construction. That is what I do for a living

Thanks for your Swift reply. I shall get in touch.
Re: Is It Realistic To Finish Building 2 Units Of 5 Bedroom Duplexes In 3 Months? by Nobody: 10:21am On Jan 19, 2022
nuland:
Hello Everyone,
I have very little knowledge about building/construction as I am into ICT.
A friend turned brother who is based in one of the Scandinavian countries has decided to return home finally this year and wants me to help him put up 2 units of 5 bedroom Duplexes.
I am based in Abuja but Our home state where the building is to be erected is less than 2 hours away, meaning I can shuttle between Abuja and home easily.
The snag is, My state is almost a civil service state where most people are government workers who rely on salaries and economic activities are at the lowest ebb you can think of. Finding building construction/construction companies that will take up the job from start to finish hasn't been fruitful.
To the professionals in the house is it feasible to get the building done in 3 Months? ( All needed for the project won't be an issue). I have asked him to give me till the end of February to do a thorough job(Findings) and get back to him.
Your Sincere Contributions shall be appreciated.
Thanks in advance!
2 months is very feasible. My cousin can mobilize his men to site and give you quality work and on time. He is in Abuja too.
Re: Is It Realistic To Finish Building 2 Units Of 5 Bedroom Duplexes In 3 Months? by Frankdesigns(m): 10:31am On Jan 19, 2022
nuland:


Thanks. no design yet but regarding design he decides who does that.
Is that phone number your WhatsApp number?

Yes

1 Like

Re: Is It Realistic To Finish Building 2 Units Of 5 Bedroom Duplexes In 3 Months? by mufutau55(m): 7:58pm On Jan 19, 2022
What State or Town will be project be?
With the full availability of fund, three months is plenty enough for the project by some of our Builders here. Look at this project below, this is in 5 days work.

https://www.nairaland.com/6866242/luxury-construction-7-bedroom-smart/2#109455507

@Dennis3D

Hajji M.
Re: Is It Realistic To Finish Building 2 Units Of 5 Bedroom Duplexes In 3 Months? by Dennis3D(m): 2:22am On Jan 20, 2022
mufutau55:
What State or Town will be project be?
With the full availability of fund, three months is plenty enough for the project by some of our Builders here. Look at this project below, this is in 5 days work.

https://www.nairaland.com/6866242/luxury-construction-7-bedroom-smart/2#109455507

@Dennis3D


Hajji M.

Thanks alot sir for the mention.
God bless you. Am deeply grateful.

As for the question. The answer is Yes to Carcass if funds are available. Though foundation has to be Raft or pad and strip to be able to meet up to that deadline or even less.
Re: Is It Realistic To Finish Building 2 Units Of 5 Bedroom Duplexes In 3 Months? by mufutau55(m): 2:48am On Jan 20, 2022
Dennis3D:

Thanks alot sir for the mention.
God bless you. Am deeply grateful.

As for the question. The answer is Yes to Carcass if funds are available. Though foundation has to be Raft or pad and strip to be able to meet up to that deadline or even less.

No.problem with that time frame if it's just carcass.
Raft or Pad foundation should not disturb the time frame at all, money moves everything.
Contact @Dennis3D with that thread for more information.

Hajji M.

1 Like

Re: Is It Realistic To Finish Building 2 Units Of 5 Bedroom Duplexes In 3 Months? by gabbytabby: 8:56am On Jan 21, 2022
I would say 4 months is a better timeframe to build in time to sink sand and dry the foundation properly and also to fully cure the decking.

1 Like

(1) (Reply)

House On A Plot Of Land @ Agbado Ijaye Ojokoro / Commercial Plots Selling At Ibeju Lekki / Buy A Plot Of Land At Mowe To Build Your House. #5M

(Go Up)

Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health
religion celebs tv-movies music-radio literature webmasters programming techmarket

Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)